Longboat Key Town Center Green Library: What November Decides

The patch of grass between Publix and the public tennis center on Town Center Green is about 28,000 square feet. On the county's drawings it already holds an 11,273-square-foot library, with a covered terrace facing the Great Lawn and a community room big enough for 200 people. The design firm has turned in 60 percent construction documents, the last submittal before the drawings are finished.

Most of the open questions about this building have been settled. The money to build it is lined up. The money to run it isn't, and it doesn't come from donors or from Town Hall. Those operating dollars come from the Sarasota County general fund, and Florida voters weigh in on the size of that fund on November 3.

What the drawings put on the corner

Twenty years of false starts led up to this, and Longboat Key News lists them: a college partnership that fell apart, two hurricanes and a long fundraising drive. The current design comes from Borrelli & Partners, according to Sarasota County's October 2026 project sheet. The sheet calls this the county's first new library location since 2018 and its first on a barrier island.

Here is what's in the plan at 600 Bay Isles Road:

  • A community room for 200. A county representative said it is "significantly larger than what we would normally build for this library." It got that size because residents at the town's 2024 workshops said they wanted a real meeting hall.
  • A covered outdoor terrace facing the Green, plus large "sitting steps" where people can read.
  • An upgraded entry. A kitchen was considered and then dropped.
  • A building pushed toward the south edge. The zoning district normally requires a 30-foot side setback. The county asked to build within 12 feet of the south property line, next to Publix Park and the Chase Bank parcel. Town staff supported the request because it keeps more open space on the Green side of the building.
  • Some tree changes. Of the 15 trees on the site, three would come out and five would be moved. Seven new ones would be planted, one more than code requires.

Pushing the building south matters for the rest of the park. The open lawn that hosts the island's holiday gathering stays open, and the building sits along the edge closest to the shopping center.

Parking relies on neighbors, not contracts

Town code requires 39 parking spaces for a library this size. That works for a normal weekday. A full community room is a different situation.

Town staff's plan for big events points to 14 neighboring properties with about 681 spaces, most of them empty after 5 p.m. Staff acknowledged the town has no contracts with those owners, only "good relationships." Under the site plan order, any large gathering would need a special-event transportation management plan through the town's permit process. The event sponsor, not the town, would arrange the borrowed parking and pay for any off-duty police.

This informal arrangement has worked on the island for years. One commissioner noted that All Angels by the Sea lent its lot for the Kiwanis Club's annual event over many seasons with only one scheduling conflict. Groups planning to book the 200-seat room should know that parking is part of the permit process, not something that comes automatically with the room.

Three pots of money, one still open

The funding has three parts. Two are settled. The third depends on the November ballot.

Piece of the project Where the money comes from Status as of October 2026
Core library building, about $11 million Sarasota County library impact fees Committed
Enhancements: larger community room, terrace, entry Private donations raised by the town and the Longboat Key Foundation Raised; $1.6 million already transferred to the county
Staff, utilities, daily operations County general fund, mostly property taxes Not yet decided

Reports give slightly different totals for the private campaign. Your Observer reported the drive raised $3.8 million against a $3 million goal, citing the town-county funding agreement. Longboat Key News puts the donor-funded enhancements at $3.5 million. Either way, the island raised the money for the extras it asked for.

As Longboat Key News put it, neither impact fees nor donations "can pay a librarian or an electric bill." County finance staff estimated operating costs at about $740,000 for a partial first year in 2028, $1.1 million in 2029 and about $1.4 million by 2031. That yearly bill is the part of the project tied to the county budget for as long as the doors are open.

Two votes about 24 hours apart

The town vote comes first. On October 5, the Town Commission unanimously advanced Ordinance 2026-13, which amends the Bay Isles planned unit development to allow a county library on the town-owned Green. It also advanced Site Development Plan Order 2026-02, the detailed site plan. Both come back for a second reading and final public hearing on Monday, November 2. The Planning and Zoning Board recommended approval 6–0 on September 15.

The statewide vote is the next day. Amendment 3 is on the November 3, 2026 ballot as "Increased Homestead Exemption; Lower Cap on Increases in Non-Homestead Property Assessments," according to the Florida Division of Elections. It would raise the homestead exemption from $50,000 to $150,000 in 2027 and $250,000 in 2028, and it needs 60 percent of the vote to pass. Sarasota County projects it would reduce county property tax revenue by about $87 million by fiscal 2029. Libraries are not among the essential services the measure tells local governments to protect.

On its Amendment 3 information page, the county lists libraries among the services that could see reduced funding or need other revenue sources, such as user fees. For the Longboat Key project specifically, Assistant Town Manager Isaac Brownman told commissioners that "the county has made it very clear" it will not build a library on Longboat Key "at this time" if Amendment 3 passes, Your Observer reported. He also said the county is still moving ahead with design, permitting and the land-use amendment "as if nothing is changing." County officials have said donors would get their money back if the project were dropped. County Administrator Jonathan Lewis told his board that no decision on operating money is needed until after the election.

The descriptions of Amendment 3 here summarize public sources and are general information, not tax or financial advice. For how any property tax change would affect your own situation, please check with a qualified tax professional.

The cottage and the oak trees run on volunteer effort

The other two fixtures on the Green this fall run the same way the library's extras were funded: through donations and volunteers.

The Longboat Key Historical Society opened its doors again in early October, according to Your Observer. The small building it occupies was originally the laundry room of the Whitney Beach Resort, built in 1926. Hours are Thursdays, Fridays and Saturdays, 11 a.m. to 1 p.m. Society President Michael Drake told the paper the first priorities for donations are a new front door and display modules for more artifacts. He also wants volunteers so he can extend the hours during season. Brownman said the planned library would not affect the cottage's location, and neither would a possible pedestrian bridge connecting the tennis center to the Green.

Light Up Longboat returns on Saturday, November 21, from 5 to 7 p.m., with food vendors, music, prizes and a tree lighting. Longboat Key News describes the free evening as organized by the Longboat Key Chamber of Commerce and the town. It includes lights strung through the Green's oak trees, hot chocolate, cake and a visit from Santa. The Longboat Key Garden Club and Save Our Seabirds are among the participating groups. This year's lighting falls in the stretch after the election and before any construction starts, so the lawn will look much as it does now.

The Green's calendar from here

  1. Thursdays through Saturdays, 11 a.m. to 1 p.m.: Historical Society cottage open.
  2. Monday, November 2: Final Town Commission hearing on Ordinance 2026-13 and Site Development Plan Order 2026-02.
  3. Tuesday, November 3: Statewide vote on Amendment 3.
  4. Saturday, November 21, 5 to 7 p.m.: Light Up Longboat on Town Center Green.
  5. Early 2027: Construction start, per the county project sheet. Town officials have suggested a groundbreaking toward the end of February, during season when the most residents are here. A September WWSB report said March.
  6. Summer 2028: Construction finish on the county's current schedule.

The lease, funding and operating agreements between the town and the county still have to be finalized as well. If the schedule holds, by summer 2028 the corner by Publix would have the first Sarasota County library on a barrier island, with a meeting room sized for the gatherings residents asked for in 2024.

If you're following how the Green, the library and the island's other civic projects will shape daily life on the key, I'm glad to talk it over. My Longboat Key neighborhood page collects more local updates, and Jayne Del Medico is always happy to share what's happening on the island. Let's Connect.

Work With Jayne

Whether it’s your first home, an upgrade, an investment property or maybe an amazing vacation home, let me help guide you to your perfect place.

Follow Me on Instagram